Project Detail
Implementaion year of this project is 2019.9.11 is owned by CHINA GEZHOUBA GROUP MECHANICAL & ELECTRICAL CONSTRUCTION CO.,LTD, Turbine Company is GOLDWIND, AGICO supplies foundation anchor cage assembly for 60 turbine foundations, includes grade 10.9 anchor bolt of M48*4530, total capacity is 48MW.
The Sun Mountain Wind Power Project is located in the Sun Mountain Immigrant Development Zone of Wuzhong City, Ningxia Hui Autonomous Region. The wind resources are abundant in the area, and the equivalent hours of wind farms can reach 2002 hours. The total installed capacity of the project is 50,000 kilowatts. It is planned to install 25 sets of wind turbines with a capacity of 2000 kilowatts. After the completion of the project, the annual power generation is expected to be 100 million kilowatt hours.
Project Detail

Three Gorges New Energy Sun Mountain Phase I 50MW Wind Power Project is located in the Sun Mountain Development Zone at the junction of Yanchi, Tongxin and Hongsibao counties (districts) in Wuzhong City, Ningxia Hui Autonomous Region. The average elevation of the project site area in this area is 1298m~1371m. The construction scale of this phase of the project is 50MW, covering an area of 7.8km2. The planned land is adjacent to Yanzhong Expressway, and the road leading to the site is currently used by Datang Wind Farm for overhauling fans, so the traffic is relatively convenient. The equipment and materials required by the wind farm can be transported to the project area through this road. AGICO supplies foundation anchor cage assembly for 60 turbine foundations, includes grade 10.9 anchor bolt of M48*4530, total capacity is 48MW. This phase of the project plans to install 25 wind turbines with a single capacity of 2000KW, an installed capacity of 50MW, and a construction period of 6 months: a 110kv step-up station will be shared with the Three Gorges New Energy Xingkengzi Phase I 30MWp photovoltaic power generation project to complete power transmission.
There are 25 fan foundations in the first phase of the wind farm, which are cast-in-situ reinforced concrete slab prestressed bolt foundation structures, with an outer diameter of 18m, a depth of 2.750m, an exposed ground of 0.850m, and a total foundation height of 3.6m (excluding cushions). . The pre-set wrong bolt assembly in the foundation, the laying bolt is connected with the upper frame.